Freedom Park Under Progress

Freedom Park Under Progress

1)Drain 750m/850m
2)Pathway-GSB laying is in progress 700m/750m and DLC work is in progress 200m/750m
3)Stage-2  nearing completion up to plinth level.
4)Stage-1 not yet started.
5)Stage-3 column casting below plinth level and SSM for footing is in progress. 
6) Mural wall column casting below plinth level is in progress. 
7)Toilet block plinth beam casting is in progress.
8)Cover slabs casting is in progress. 

Physical progress: 30%
Financial progress: 20%